Rosenblatt
  • About
    • Memery Crystal
    • Investors
  • Services

    Services

    Rosenblatt is a disputes powerhouse. Competitive in the best sense, our teams provide incisive specialist expertise and collaborate closely with one another to meet our clients’ needs across the full spectrum of their activities.

    • Dispute Resolution
    • Construction, Engineering and Energy
    • Corporate Investigations
    • Debt Recovery
    • DLT, Digital Assets, and Tokenisation
    • Financial Crime
    • Financial Services
    • Insolvency & Financial Restructuring
    • International Arbitration
    • Probate & Wills
    • Serious & General Crime
    • Tax
    • Non-Contentious & Advisory
  • Insight
  • Events
  • Group Litigation
    • Amazon Legal Action
    • Property Investment Scheme Claims
    • Apple Class Action
  • Contact

Can’t Pay or Won’t Pay – Court Confirms Insolvency Proceedings are not Appropriate for Enforcing Debts due under Construction Contracts

5th June 2017

Parties should settle construction disputes through adjudication or Court proceedings, according to High Court Judge

Daniel Alexander QC, sitting as a Deputy Judge of the Chancery Division, has provided further clarification on the appropriate avenue for parties to contest debts arising from construction contracts. In his Judgment in the recent decision, Breyer Group plc v RBK Engineering Ltd [2017] EWHC 1206 (Ch) (19 May 2017), Alexander QC stated that it would constitute “an abuse of process” for a party to pursue a winding-up petition against a debtor in circumstances where it is “not a case of can’t pay, but won’t pay.” The proper place to settle such a dispute is either through adjudication or Court proceedings.

Origins of the dispute

Breyer Group plc (“Breyer”) was a contractor on a building project and had appointed RBK Engineering Ltd (“RBK”) in May 2015 as a sub-contractor to carry out certain refurbishment and electrical works. The appointment was formalised at the time by a contract between the parties containing standard terms and conditions, including terms relating to payment (including interim payment) and an express dispute resolution clause.

The work performed by RBK continued beyond the term of the contract, late into 2016. However, although a subsequent draft contract was never signed by either Breyer or RBK, it was clear both parties considered the relationship to be governed by the terms of the original contract.

By the end of 2016, a dispute had arisen between the parties with Breyer contesting the contents of RBK’s payment applications and alleging that RBK had carried out defective works, which Breyer would have to remedy at its own cost. In December 2016 the parties entered into a settlement agreement, which included provisions setting out a number of payments to be made by Breyer to RBK. Ultimately, however, on 1 March 2017, when the final payment was due, Breyer served a Pay Less Notice on RBK, which in fact required RBK to settle a small balance to Breyer arising from the defects which had been disputed between the parties.

The winding-up petition

The parties failed to reach an agreement and on 22 March 2017, RBK filed a winding-up petition against Breyer, claiming the contractor was indebted to it in the sum of £258,729.16. However, following the application of Breyer and an assessment of its finances, the Deputy Judge elected to strike out the winding up petition.

Alexander QC’s Judgment

In his Judgment, Alexander QC concluded that Breyer was “plainly not insolvent in the sense of being unable to pay the alleged debt.” Rather, a “genuine dispute” had arisen between the parties, to which Beyer had arguable defences and substantial cross-claims of its own.  Breyer’s position was predicated on its concerns regarding the quality of RBK’s electrical works, together with a dispute about which contract terms were operative. To, therefore, continue insolvency proceedings in such circumstances would be “oppressive” and an inappropriate forum for settling the dispute. Instead, Alexander QC held, the dispute could be readily resolved either through adjudication or Court proceedings.

In conclusion, where a dispute is purely about money and late payment, issuing a statutory demand for payment can be a cost-effective and straightforward way to seek to extract a timely settlement. However, should a dispute resulting in unpaid monies actually concern “won’t pay” issues, as was the case in Breyer, then the Court has made clear that the proper forum to seek resolution is adjudication or litigation. It appears as though the Court has one eye on seeking to dissuade parties from using the commercial threat of a winding-up petition in circumstances where there are more substantive issues to be ventilated.

Adjudication

Adjudication is a prescribed “fast track” procedure designed to settle disputes arising from a construction contract. Adjudication is available to all parties to a construction contract unless one of the contracting parties is a residential occupier or another exclusion is applicable. Statutory adjudication was introduced by the Housing Grants, Construction and Regeneration Act 1996 (the “Construction Act”), with the Scheme for Construction Contracts Regulations 1998 (the “Scheme”) providing the procedural fall back in the event that the construction contract in question does not contain all of the adjudication provisions of the Construction Act.

Pursuant to the Construction Act, any party to a construction contract has the right to refer a dispute to adjudication. Typically, adjudication will last only 28 days, although it is possible for the parties to extend this period by agreement.

Under the Scheme, the parties appoint an adjudicator to consider the issues in dispute, with the decision treated as interim-binding (unless the construction contract provides otherwise), meaning an adjudication decision is binding until finally determined by legal proceedings, arbitration or agreement. A successful party will most commonly seek to enforce an adjudicator’s decision in the Technology and Construction Court.

Rosenblatt offers expertise on all forms of construction disputes, including adjudication and arbitration, as well as court proceedings in complex and multijurisdictional litigation, supported by its Dispute Resolution team. The firm has extensive experience in the Technology and Construction Court.

The content of this bulletin should not be construed as legal advice. If you do require legal advice, please contact a solicitor at Rosenblatt.

Post navigation

Liquidated damages: how much is too much?
Senior Management of the Parts Alliance Group sell their shareholding to Uni-Select Inc.

Categories

  • Articles
  • News
  • Videos

Topics

  • Banking & Finance
  • Competition & Regulatory
  • Corporate
  • Dispute Resolution
  • DLT, Cryptocurrencies and Crypto Assets
  • Employment
  • Financial Crime
  • Financial Services
  • Insolvency & Financial Restructuring
  • International Arbitration
  • Investigations
  • IP/Technology/Media
  • Real Estate
  • Tax
Rosenblatt
  • +44 (0) 20 7955 0880
  • info@rosenblatt-law.co.uk

Helpful Links

  • Anti-Modern Slavery Statement
  • Complaints Policy
  • Diversity & Equality
  • Interest
  • Pricing
  • Subscribe to our Mailing List

SRA No. 820215, authorised and regulated by the Solicitors Regulation Authority.

Ce Logo
Uk Top Tier Firm 2026

Rosenblatt is a trading name of RBG Legal Services Limited, a company registered in England and Wales (with company number 13287062) and which is authorised and regulated by the Solicitors Regulation Authority under SRA No. 820215. A list of the directors of RBG Legal Services Limited, together with a list of those persons who are designated as partners of Rosenblatt, is available for inspection at the registered office of the company at 165 Fleet Street, London EC4A 2DY.

Rosenblatt uses the word “partner” to refer to a senior employee or consultant. However, Rosenblatt is not a partnership and the use of the term “partner” does not create or imply a partnership amongst or between any of its employees or consultants.

© 2025 Rosenblatt

  • Privacy Policy
  • Cookie Policy
  • Terms & Conditions

Website by Brighter*IR

link

We are using cookies to give you the best experience on our website.

You can find out more about which cookies we are using or switch them off in .

Rosenblatt
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookies should be enabled at all times so that we can save your preferences for cookie settings.

If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.

Performance cookies

These cookies allow us to count visits and traffic so we can measure and improve the performance of our site. They help us to know which pages are the most and least popular and see how visitors move around the site.

Please enable Strictly Necessary Cookies first so that we can save your preferences!

Cookie Policy

More information about our Cookie Policy.